Road Program

Doylestown Township Road Program

We Care about your Roads

We make every effort to renew the roads in Doylestown Township. We work every year to identify those roads needing paving. We take into consideration the amount of traffic on a road, the weather from the previous winter, and the results of our road surveys. We also take into account feedback we receive from our residents.

2025 Road Program

The Board of Supervisors adopted the 2025 Road Program on June 17, 2025. Bids were received on Tuesday, June 10th, with James D. Morrissey, Inc. of Philadelphia, PA, submitting the low bid. The total contract cost, including the base bid and three alternates is $850, 971.00.

The Road Program is scheduled to begin on August 28 and continue through September 12 with milling and paving work.

Milling Schedule

  • Thursday, August 28 – East Butler (start Shady Retreat)
  • Friday, August 29 – Shady Retreat & Countrybrook Drive
  • Tuesday, September 2 – Mahogany Court & North Shady Retreat
  • Wednesday, September 3 – Pine Valley (Mill & Fill)
  • Thursday, September 4 – Pine Valley (Mill & Fill)
  • Friday, September 5 – Pinevale (Mill & Fill)

Paving Schedule

  • Monday, September 8 – East Butler
  • Tuesday, September 9 – Shady Retreat
  • Wednesday, September 10 – Shady Retreat & Countrybrook Drive
  • Thursday, September 11 – Mahogany Court & North Shady Retreat
  • Friday, September 12 – North Shady Retreat

Click Here to view the Road Program Map