Pebble Ridge / Woodridge and Vicinity Sewer Project

  1. Home
  2. Information
  3. Pebble Ridge / Woodridge and Vicinity Sewer Project
Find information regarding the Pebble Ridge/ Woodridge and Vicinity Sewer Project.
FAQ
How do I Connnect?
Updates from BCWSA
Sewer Progress Map
Road Program Curbing and Paving Projects
Construction Drawings for Pebble Ridge/Woodridge Area Sanitary Sewers
PENNVEST Loan Information
Ordinances
Presentations & Other Information
How do I Connnect?

Once the sewer line in front of your property has been completed you may want to consider connecting to the system. If so you may be wondering how you go about making the connection. Remember it is not necessary to connect if the On Lot Disposal System (OLDS) on your property is working properly.  Here are the steps you need to follow to make the connection.

  1. Contact Bucks County Water and Sewer Authority (BCWSA) at 215-343-2538 and request an EDU (Equivalent Dwelling Unit) for your property. Please provide your name, address, phone and an email.
  2. Obtain an invoice from BCWSA that confirms you’ve made the request for the EDU.
  3. Your or your plumber can bring the BCWSA Invoice indicating that you’ve requested the EDU to the Doylestown Township Code Department to obtain a plumbing permit for the lateral connection. Permit fee is $89.50
  4. When your plumber has completed the connection contact the Doylestown Township Code Department for a final inspection.
  5. When the connection inspection is complete you will receive a Certification of Completion from the Doylestown Township Code Department.
  6. Provide a copy of the Certificate of Completion to the BCWSA.
  7. BCWSA will then expect payment of the original invoice ($6,200) for the EDU they issued. You will have thirty (30) days in which to pay BCWSA for the EDU. Your property will then be put into the BCWSA system for monthly billing for sewage use.
  8. You can obtain a Septic Tank Closure Permit with instructions on how to close your septic tank from the Bucks County Health Department by calling (215) 345-3318.
  9. Proceed with decommissioning your Septic Tank
  10. Flush Away.
Updates from BCWSA

BCWSA Employees will be putting safety protocols for the Coronavirus in place on the job site. They will be wearing gloves, keeping distance between each other when possible and as appropriate wiping down equipment and vehicles while in use. Interaction with residents is to be postponed. If a lateral location needs to be adjusted any interaction between residents and BCWSA personnel will be done with the appropriate social distancing and protection needed for safety . 

Weekly Updates

September 11, 2020

The crew installed 224LF of sewer main and 220LF of force main and MH#45 on Westaway. The crew installed 6 laterals on Willow. Drilling on Willow near Westaway is continuing. The rig brokedown so the final drilling will end early next week. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Meetings with residents in the construction area for lateral location stakes is continuing.  The project is currently on budget but behind schedule about 9 weeks.

In the next  week weather and conditions permitting we will expect to Install:

– Continue working up Westaway installing sewer and force main from MH#45 and install MH#46. Continue force main to Woodridge.

–   Continue working on Willow. Install Laterals in the areas where the main is completed to allow for water main work to begin.

– Install sewer main on Willow from Westaway to complete all main work on Willow.

– Continue meeting with residents (applying social distancing) to identify lateral location and depth

-Drilling on Willow Lane. (should be completed by Tuesday)

Please Note: Residents on Willow will not be able to hook up to the sewer until the lower part of the easement line is completed over the next few months.

September 4, 2020

The crew installed 226LF of sewer main and 230LF of force main on Westaway. The crew installed 394LF of sewer main on Willow. Main installation on Willow towards Woodridge is completed. Drilling on Willow near Westaway is continuing. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Meetings with residents in the construction area for lateral location stakes is continuing.  The project is currently on budget but behind schedule about 9 weeks.

In the next  week weather and conditions permitting we will expect to Install:

– Continue working up Westaway installing sewer and force main from MH#45 and install MH#46. Continue force main to Woodridge.

–  Continue working on Willow. Install Laterals in the areas where the main is completed to allow for water main work to begin.

–  Continue meeting with residents (applying social distancing) to identify lateral location and depth.

–  Drilling on Willow Lane.

Please Note: Residents on Willow will not be able to hook up to the sewer until the lower part of the easement line is completed over the next few months.

August 21, 2020

The crew installed 280LF of sewer main and 280LF of force main on Westaway. The crew installed 380LF of sewer main on Willow. Drilling on Willow near Westaway is continuing. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Meetings with residents in the construction area for lateral location stakes is continuing.  The project is currently on budget but behind schedule about 9 weeks.

In the next  week weather and conditions permitting we will expect to Install:

– Continue working up Westaway installing sewer and force main from MH#43 and install MH#44. Then continue to MH#45

– Continue working on Willow. Install MH#80 and continue installing main up to MH#81 towards S. Woodridge.

– Continue meeting with residents (applying social distancing) to identify lateral location and depth.

– Drilling on Willow Lane.

Please Note: Residents on Willow will not be able to hook up to the sewer until the lower part of the easement line is completed over the next few months.

August 7, 2020

The crew installed 224LF of sewer main and 220LF of force main on Westaway. They are moving well through the predrilled rock. Due to continued emergency sewer main repairs down county no other work was performed this week. Drilling on Old New Road will continue and move to the portion of Willow near Westaway. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Meetings with residents in the construction area for lateral location stakes is continuing.  The project is currently on budget but behind schedule about 9 weeks.

In the next  week weather and conditions permitting we will expect to Install:

–  A portion of Old New Road between Bristol and Westaway will be down to one lane at 8:00 am until 4:00pm Monday and Tuesday of next week.

– Continue working up Westaway installing sewer and force main from MH#40 towards MH#41.

–  Installing lateral stubs behind the curbs on Willow. Pipe installation will restart on Willow when lateral stubs are caught up.

– Continue meeting with residents (applying social distancing) to identify lateral location and depth.

– Drilling on Old New Road and Westaway Lane.

July 31, 2020

The crew installed 138LF of sewer main and 140LF of force main as well as MH#40 on Westaway. Due to continued emergency sewer main repairs down county no other work was performed this week. Drilling on Old New Road will continue. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Meetings with residents in the construction area for lateral location stakes is continuing.  The project is currently on budget but behind schedule about 9 weeks.

In the next week weather and conditions permitting we will expect to Install:

–  A portion of Old New Road between Bristol and Westaway will be down to one lane at 8:00 am until 4:00pm Monday thru Friday until the drilling is completed.

– Continue working up Westaway installing sewer and force main from MH#40 towards MH#41.

– 150 LF of sewer main towards MH#80 on Willow Lane. (if we complete the down county work before the end of this week)

-Continue meeting with residents (applying social distancing) to identify lateral location and depth.

– Drilling on Old New Road.

July 27, 2020

The crew installed 10LF of sewer main and MH#79 on Willow lane. Road. Due to continued emergency sewer main repairs down county no other work was performed this week. the crews will be back on site on Monday. Drilling on Old New Road will continue next week. Partial road closure of Old New Road should be completed next week. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Meetings with residents in the construction area for lateral location stakes is continuing.  The project is currently on budget but behind schedule about 9 weeks.

In the next  week weather and conditions permitting we will expect to Install:

  A portion of Old New Road between Bristol and Westaway will be closed starting on 7-20-20 at 8:00 am until 4:00pm Monday thru Friday until the main is installed.

– Begin working up Westaway installing sewer and force main from MH#25 on Old New Road.

– 150 LF of sewer main towards MH#80 on Willow Lane.

– Continue meeting with residents (applying social distancing) to identify lateral location and depth.

– Drilling on Old New Road.

 

July 17, 2020

The crew installed 35LF of sewer main and MH#26 on Old New Road. Due to emergency sewer main repairs down county no other work was performed this week. the crews will be back on site on Monday. Drilling on Old New Road will continue next week. Partial road closure of Old New Road should be completed next week. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Meetings with residents in the construction area for lateral location stakes is continuing.  The project is currently on budget but behind schedule about 9 weeks.

In the next week weather and conditions permitting we will expect to Install:

–  A portion of Old New Road between Bristol and Westaway will be closed starting on 7-20-20 at 8:00 am until 4:00pm Monday thru Friday until the main is installed.

– Begin working up Westaway installing sewer and force main from MH#25 on Old New Road.

– 150 LF of sewer main towards MH#79 on Willow Lane.

-Continue meeting with residents (applying social distancing) to identify lateral location and depth.

-Drilling on Old New Road.

Phil crew installed 35 lf of 8″ SDR 35 Pipe and 2 lateral tees and installed Manhole #26 on Monday.

July 10, 2020

The crew installed 182LF of sewer main, 184LF of force main and MH#25 on Old New Road. The second crew installed 136LF of sewer main and MH#77 and MH#78 on Willow Lane. Rock in Willow Lane and Old New Road is slowing production. Drilling on Old New Road is continuing. Road closure of Old Bew Road should be completed next week. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Meetings with residents in the construction area for lateral location stakes is continuing.  The project is currently on budget but behind schedule about 8 weeks.

In the next  week weather and conditions permitting we will expect to Install:

– Old New Road will be closed starting on 5-26-20 at 8:00 am until 4:00pm Monday thru Friday until the main is installed.

–  The remaining footage to and install MH#26 on Old New Road. Then begin up Westaway.

–  150 LF of sewer main towards MH#79 on Willow Lane.

– Continue meeting with residents (applying social distancing) to identify lateral location and depth.

–  Drilling on Old New Road.

July 2, 2020

* Friday July 3rd is a holiday – no work will be performed.

The crew installed 138LF of sewer main, 140LF of force main and MH#24 on Old New Road. The second crew installed 69LF of sewer main and continued on Willow towards MH#77 on Willow Lane. Rock in Willow Lane and Old New Road is slowing production. Drilling on Old New Road is continuing. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Meetings with residents in the construction area for lateral location stakes is continuing.  The project is currently on budget but behind schedule about 8 weeks.

In the next  week weather and conditions permitting we will expect to Install:

– Old New Road will be closed starting on 5-26-20 at 8:00 am until 4:00pm Monday thru Friday until the main is installed.

-The remaining footage to and install MH#25 on Old New Road.

– 150 LF of sewer main towards MH#78 on Willow Lane.

– Continue meeting with residents (applying social distancing) to identify lateral location and depth.

– Drilling on Old New Road.

June 26, 2020

The crew installed 156LF of sewer main, 160LF of force main and continued towards MH#24 on Old New Road. The second crew installed 100LF of sewer main and MH#76 on Willow Lane. Rock in Willow Lane and Old New Road is slowing production but we are making better progress than last week. Restoration of the 1st leg of the easement area was completed from Lower State Road to the upper section of Old New Road. 2nd leg still to be completed. Drilling on Old New Road is continuing. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Meetings with residents in the construction area for lateral location stakes is continuing.  The project is currently on budget but behind schedule about 8 weeks.

In the next  week weather and conditions permitting we will expect to Install:

– Old New Road will be closed starting on 5-26-20 at 8:00 am until 4:00pm Monday thru Friday until the main is installed.

– MH PS-24 and the remaining footage to MH#25 on Old New Road.

– 150 LF of sewer main towards MH#77 on Willow Lane.

– Continue meeting with residents (applying social distancing) to identify lateral location and depth.

– Drilling on Old New Road.

June 19, 2020

The crew installed 102LF of sewer main, 102LF of force main and MH#23 on Old New Road. The second crew installed 137LF of sewer main and MH#75 on Willow Lane. Rock in Willow Lane and in Old New Road is slowing production but we are making better progress than last week. Restoration of the 1st leg of the easement area was completed from Lower State Road to the upper section of Old New Road. 2nd leg still to be completed. Drilling on Willow Lane is continuing on Old New Road. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Meetings with residents in the construction area for lateral location stakes is continuing.  Westaway was swept on Thursday this week due to weather. The project is currently on budget but behind schedule about 8 weeks.

** 5-22-20 A special note for the residents of Westaway. We realize you have endured, and continue to endure the conditions during the drilling and the aftermath. We appreciate your continued patience. The crews will be sweeping every Friday and will do all they can to reduce the dust and stones. Unfortunately we can’t eliminate it completely but we will do our best. We expect to be installing sewer and force main on Westaway at Old New Road in 3 – 4 weeks. We expect to complete the sewer main and force main installation on Westaway 4-5 weeks after we start. Rock encountered and weather will affect the schedule.  **

In the next  week weather and conditions permitting we will expect to Install:

– Old New Road will be closed starting on 5-26-20 at 8:00 am until 4:00pm Monday thru Friday until the main is installed.

–  MH PS-24 and 100 LF of sewer and force main towards MH#25 on Old New Road.

– MH76 and 200 LF of sewer main towards MH#77 on Willow Lane.

– Continue meeting with residents (applying social distancing) to identify lateral location and depth.

– Drilling on Old New Road.

June 12, 2020

The crew installed 126LF of sewer main, 126LF of force main moving towards MH#23 on Old New Road. The second crew installed 152LF of sewer main moving towards and MH#75 on Willow Lane. Rock in Willow Lane and in Old New Road is slowing production but we are making better progress than last week. Restoration of the 1st leg of the easement area was completed from Lower State Road to the upper section of Old New Road. Drilling on Willow Lane is continuing and will move to Old New Road. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Meetings with residents in the construction area for lateral location stakes is continuing.  Westaway will be swept every friday. The project is currently on budget but behind schedule about 8 weeks.

** 5-22-20 A special note for the residents of Westaway. We realize you have endured, and continue to endure the conditions during the drilling and the aftermath. We appreciate your continued patience. The crews will be sweeping every Friday and will do all they can to reduce the dust and stones. Unfortunately we can’t eliminate it completely but we will do our best. We expect to be installing sewer and force main on Westaway at Old New Road in 3 – 4 weeks. We expect to complete the sewer main and force main installation on Westaway 4-5 weeks after we start. Rock encountered and weather will affect the schedule.  **

In the next  week weather and conditions permitting we will expect to Install:

– Old New Road will be closed starting on 5-26-20 at 8:00 am until 4:00pm Monday thru Friday until the main is installed.

-MH PS-23 and 100 LF of sewer and force main towards MH#24 on Old New Road.

-MH75 and 200 LF of sewer main towards MH#76 on Willow Lane.

-Continue meeting with residents (applying social distancing) to identify lateral location and depth.

– Drilling on Willow Lane.

June 5, 2020

– Old New Road will be closed starting on 5-26-20 at 8:00 am until 4:00pm Monday thru Friday until the main is installed.

-MH PS-23 and 100 LF of sewer and force main in Old New Road.

-MH75 and 200 LF of sewer main on Willow Lane.

-Continue meeting with residents (applying social distancing) to identify lateral location and depth.

-Begin the restoration of the driveway area and easement area from Lower State Road up to Old New Road as weather permits. (Next week)

-Drilling on Willow Lane.

June 1, 2020

The crew installed 82LF of sewer main, 85LF of force main and MH#20. they have moved out of the easement and on to Old New Road. The second crew installed 82LF of sewer main on Willow Lane. Rock in Willow Lane and in Old New Road is slowing production. Drilling on Willow Lane is continuing and will move to Old New Road. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Meetings with residents in the construction area for lateral location stakes is continuing.  Westaway will be swept every friday. The project is currently on budget but behind schedule about 8 weeks.

 

** 5-22-20 A special note for the residents of Westaway. We realize you have endured, and continue to endure the conditions during the drilling and the aftermath. We appreciate your continued patience. The crews will be sweeping every Friday and will do all they can to reduce the dust and stones. Unfortunately we can’t eliminate it completely but we will do our best. We expect to be installing sewer and force main on Westaway at Old New Road in 3 – 4 weeks. We expect to complete the sewer main and force main installation on Westaway 4-5 weeks after we start. Rock encountered and weather will affect the schedule.  **

 

In the next  week weather and conditions permitting we will expect to Install:

 

-Old New Road will be closed starting on 5-26-20 at 8:00 am until 4:00pm Monday thru Friday until the main is installed.

-MH PS-21 and 100 LF of sewer and force main in Old New Road.

MH73 and 200 LF of sewer main on Willow Lane.

-Continue meeting with residents (applying social distancing) to identify lateral location and depth.

-Begin the restoration of the driveway area and easement area from Lower State Road up to Old New Road as weather permits. (in next 10 days)

-Drilling on Willow Lane as progress allows.

May 22, 2020

In the next  week weather and conditions permitting we will expect to Install:

  Old New Road will be closed starting on Tuesday Morning at 8:00 am until 4:00pm/ Tuesday thru Friday.

– MH PS-20 and 150 LF of sewer and force main in the easement area and proceeding up to and onto Old New rd.

-MH72 and 200 LF of sewer main on Willow Lane.

-Continue meeting with residents (applying social distancing) to identify lateral location and depth.

– Begin the restoration of the driveway area and easement area from Lower State Road up to Old New Road as weather permits. (in next 10 days)

-Drilling on Willow Lane as progress allows.

May 15, 2020

The crew installed 267LF of sewer main and 270LF of force main as well as MH #18 and MH#19 in the easement. The second crew installed 98LF of sewer main and MH #73 on Willow Lane. Weather continues to slow progress in the easement area. Rock in Willow Lane is slowing production. Drilling on Willow Lane is continuing and will move to Old New Road. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Meetings with residents in the construction area for lateral location stakes is continuing.

In the next  week weather and conditions permitting we will expect to Install:

-MH PS-20 and 300 LF of sewer and force main in the easement area and proceeding up to and onto Old New rd.

-MH72 and 300 LF of sewer main on Willow Lane.

– Continue meeting with residents (applying social distancing) to identify lateral location and depth.

– Begin the restoration of the driveway area and easement area from Lower State Road up to Old New Road as weather permits. (in next 10 days)

– Drilling on Willow Lane as progress allows.

May 8, 2020

In the next  week weather and conditions permitting we will expect to Install:

–  MH PS-18 and 300 LF of sewer and force main in the easement area and proceeding up to Old New rd.

–   2MH 73 and 250 LF of sewer main and additional manholes on Willow Lane.

–  Continue meeting with residents (applying social distancing) to identify lateral location and depth.

–  Begin the restoration of the driveway area and easement area from Lower State Road up to Old New Road as weather permits.

–  Continue meeting with residents (applying social distancing) to identify lateral location and depth

–  Drilling on Willow Lane as progress allows.

May 1, 2020

The crew installed 259LF of sewer main and force main in the easement and on Willow Lane. One MH on Willow Lane and one MH on the easement. In the easement area we are still experiencing blue rock at 3 feet above invert as well as significant water in the trench. Weather continues to slow progress in the easement area as well. Drilling on Willow Lane is continuing and will move to Old New Road. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Meetings with residents in the construction area for lateral location stakes is continuing.

In the next  week weather and conditions permitting we will expect to Install:

–  MH PS-17 and 300 LF of sewer and force main in the easement area and proceeding up to Old New rd.

–  250 LF of sewer main and additional manholes on Willow Lane towards Westaway. We will then move to mid-way down Willow and work back towards Woodridge.

–  Continue meeting with residents (applying social distancing) to identify lateral location and depth.

–  Drilling on Willow Lane as progress allows.

April 24, 2020

The crew installed 142 LF of sewer main and force main in the easement and on Willow Lane. Two MH’s on Willow Lane. All Lateral stubs on Woodridge Drive are completed. In the easement area we are still experiencing blue rock at 4 feet above invert as well as significant water in the trench. Weather continues to slow progress in the easement area as well. We were able to get a few good work days in there this week. Drilling on Westaway is continuing and will move to Willow Lane shortly. Street sweeping of Westaway where the drilling took place is also complete. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Meetings with residents in the construction area for lateral location stakes is continuing.

In the next  week weather and conditions permitting we will expect to Install:

–  MH PS-16 and 250 LF of sewer and force main in the easement area and proceeding up to Old New rd.

–  300 LF of sewer main and additional manholes on Willow Lane towards Westaway. We will then move to mid-way down Willow and work back towards Woodridge.

–  Install lateral stubs on in easement area for the two property owners adjacent to the easement.

–  Continue meeting with residents (applying social distancing) to identify lateral location and depth.

–  Saw Cutting on Westaway then Willow Lane will continue to stay ahead of the drill rig.

–   Drilling on Westaway then Willow Lane as progress allows.

 

April 17, 2020

The crew installed the last 100 LF of sewer main and the last MH on Woodridge Drive. Crews began excavating on Willow Lane. All Lateral stubs on Woodridge Drive are completed. Cold patching of Stony Lane Circle was completed. We are still experiencing blue rock at 4 feet above invert as well as significant water in the trench and muddy conditions due to weather preventing us from working in the easement area off Lower State Road at this time. Drilling on Westaway is continuing and will move to old New Road. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Meetings with residents in the construction area for lateral location stakes is continuing.

In the next  week weather and conditions permitting we will expect to Install:

–    MH PS-15 with sewer and force main at the second stream crossing in the easement between Lower State rd. and Old New rd. (on hold due to conditions)

–   3000 LF of sewer main and MH #68 and MH# 69 on Willow Lane and begin working back towards Woodridge.

–  Clean up and cold patching of Woodridge as weather allows.

–  Continue meeting with residents (applying social distancing) to identify lateral location and depth.

–   Saw Cutting on Willow will continue to stay ahead of the drill rig.

–  Drilling on Westaway then Willow as progress allows.

April 9, 2020

The crew installed 380 LF of main and two MH’s on Woodridge Drive. All Lateral stubs on Stony Lane Circle are completed. We are still experiencing blue rock at 4 feet above invert as well as significant water in the trench and muddy conditions due to weather preventing us from working in the easement area off Lower State Road at this time. Drilling on Westaway is continuing. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Meetings with residents in the construction area for lateral location stakes is continuing.

In the next  week weather and conditions permitting we will expect to Install:

–  MH PS-15 with sewer and force main at the second stream crossing in the easement between Lower State rd. and Old New rd. (on hold due to conditions)

– 100 LF of sewer main and final MH on Woodridge Drive. We will then move to mid-way down Willow and begin working back towards Woodridge.

–   Continue installing lateral stubs on Woodridge Drive.

–    Clean up and cold patching of Stony Lane Circle and other areas of the project that need touch up.

–    Continue meeting with residents (applying social distancing) to identify lateral location and depth.

–   Saw Cutting on Westaway then Willow will continue to stay ahead of the drill rig.

–  Drilling on Westaway then Willow as progress allows.

April 3 ,2020

The crew installed 450 LF of main on Stony Lane Circle and Woodridge. All Manholes have been installed on Stony Lane Circle. No pipe was installed on the easement due to wet conditions.  Drilling on Westaway is continuing. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Meetings with residents in the construction area for lateral location stakes is continuing.

In the next  week weather and conditions permitting we will expect to Install:

–  200 LF of Sewer and force main at the second stream crossing in the easement between Lower State rd. and Old New rd.

–  500 LF of sewer main on Woodridge.

–  continue installing laterals on Stony Lane Circle.

–   (when needed) Continue meeting with residents (applying social distancing) to identify lateral location and depth.

–  Saw Cutting on Westaway will continue to stay ahead of the drill rig.

–  Drilling on Westaway will continue.

March 27, 2020

In the next  week weather and conditions permitting we will expect to Install:

–  MH PS-15 with sewer and force main at the second stream crossing in the easement between Lower State rd. and Old New rd.

– 120 LF of sewer main and the remaining MH #41 on Stony Lane Circle.

– Begin installing main from Stony Lane Circle on Woodridge to Willow.

– Continue meeting with residents (applying social distancing) to identify lateral location and depth.

–  Saw Cutting on Westaway will continue to stay ahead of the drill rig.

– Drilling on Westaway will continue.

March 20, 2020

The crew installed 180 LF of main and MH#40 on Stony Lane Circle. 100 LF of force main and sewer main was installed into MH#7 and main into MH#PS 15. We are still experiencing blue rock at 4 feet above invert as well as significant water in the trench on the easement off Lower State Road. Drilling on Westaway is continuing. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Meetings with residents in the construction area for lateral location stakes is continuing.

In the next  week weather and conditions permitting we will expect to Install:

DUE TO THE GOVERNORS DIRECTIVE THE PROJECT HAS BEEN SHUT DOWN UNTIL FURTHER NOTICE STARTING MONDAY 3-23-20.

March 13, 2020

The crew installed 201 LF of main and MH#39 on Stony Lane Circle. 128 LF of force main and sewer main was installed to MH#7 and main up to MH#PS 15. We are still experiencing blue rock at 4 feet above invert as well as significant water in the trench on the easement off Lower State Road. Drilling on Westaway is continuing. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Meetings with residents in the construction area for lateral location stakes is continuing.

In the next  week weather and conditions permitting we will expect to Install:

– MH PS-15 with sewer and force main at the second stream crossing in the easement between Lower State rd. and Old New rd.

– 300 LF of sewer main and the remaining MH’s40 & 41 on Stony Lane Circle.

-Continue meeting with residents to identify lateral location and depth.

– Saw Cutting on Westaway will continue to stay ahead of the drill rig.

-Drilling on Westaway will continue.

March 6, 2020

The crew installed 272 LF of main and MH#37 & MH# 38 on Stony Lane Circle. 140 LF of force main and sewer main was installed to MH#6. A stream crossing for the main up MH#6 was completed and the run towards MH#7 was started. We are still experiencing blue rock at 4 feet above invert as well as significant water in the trench on the easement off Lower State Road. Drilling on Westaway is continuing. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Meetings with residents in the construction area for lateral location stakes is continuing.

In the next  week weather and conditions permitting we will expect to Install:

-MH PS-7 and MH#8 with sewer and force main where it crosses the second stream in the easement between Lower State rd. and Old New rd.  and up to MH#7 on Old New Road’

– 500 LF of sewer main and the remaining MH’s on Stony Lane Circle.

-Continue meeting with residents to identify lateral location and depth.

-Letters to residents on Willow Lane for lateral locations will go out today

– Saw Cutting on Westaway will continue to stay ahead of the drill rig.

– Drilling on Westaway will continue.

March 2, 2020

The crew installed 360 LF of main and MH#33 on Woodridge down to and onto Stony Lane Circle. 120 LF of force main was installed to MH#5. A stream crossing for the force main up MH#6 was set up. We are still experiencing blue rock at 4 feet above invert as well as significant water in the trench on the easement off Lower State Road. Drilling on Westaway is continuing. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Meetings with residents in the construction area for lateral location stakes is continuing.

In the next  week weather and conditions permitting we will expect to Install:

-MH PS-6 sewer and force main where it crosses the stream in the easement between Lower State rd. and Old New rd.

-800 LF of sewer main on Stony Lane Circle.

-Continue meeting with residents to identify lateral location and depth.

-Saw Cutting on Westaway will continue to stay ahead of the drill rig.

-Drilling on Westaway will continue.

February 24, 2020

The remaining lateral stubs were installed on Woodridge near Buck road. The remaining sewer main was installed from Manhole #5 to Manhole #6 short of the stream in the easement off Lower State Road. We are still experiencing blue rock at 4 feet above invert as well as significant water in the trench on the easement off Lower State Road. Drilling on Westaway is continuing. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Meetings with residents in the construction area for lateral location stakes is continuing.

In the next  week weather and conditions permitting we will expect to Install:

– MH PS-6 and sewer and force main where it crosses the stream in the easement between Lower State rd. and Old New rd.

  •  200 LF of sewer main on Woodridge from Stony Lane towards Turk road to MH#33.

– Continue meeting with residents to identify lateral location and depth.

– Saw Cutting on Woodridge and Stony Lane Circle will begin.

– Drilling on Westaway will continue.

February 14, 2020

2 lateral stubs were installed on Woodridge near Buck road. 42LF of sewer main and force main was installed in the easement off Lower State Road. We are still experiencing blue rock at 4 feet above invert as well as significant water in the trench on the easement off Lower State Road. We lost 2 days of work due to weather and one day due to an emergency sewer dig up in Bensalem. Drilling on Westaway is continuing. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Meetings with residents in the construction area for lateral location stakes is continuing.

In he next  week weather and conditions permitting we will expect to Install:

– Remaining lateral stubs on Woodridge section with main installed.

–  MH PS-5 and sewer and force main to MH PS-6 in the easement between Lower State rd. and Old New rd.

–  200 LF of sewer main on Woodridge from Stony Lane towards Turk road.

–  Continue meeting with residents to identify lateral location and depth.

– Saw Cutting on Woodridge and Westaway will continue.

– Drilling on Westaway will continue.

February 07, 2020

196LF of pipe was installed on Woodridge and MH #32 near Buck Road.  70LF of sewer main and force main was installed in the easement off Lower State Road.  We are still experiencing blue rock at 4 feet above invert as well as significant water in the trench on the easement off Lower State Road.  MH#4 in the easement needed to be wrapped on the outside with special material from the manufacture due to the high hydrostatic pressure from the surrounding ground water.  Test pits for soil sampling will continue on Monday and Tuesday of next week. Drilling on Westaway is continuing.  Erosion and sedimentation controls were checked to protect the creek from runoff and inlet covers were checked.  Meetings with residents in the construction area for lateral location stakes is continuing.

In the next week weather and conditions permitting we will expect to install:

-100 Lf of sewer main Woodridge from Manhole #30 towards Turk Road

-MH PS-5 and sewer and force main to MH PS-6 in the easement between Lower State Road and Old New Road

-Lateral stubs for the properties on Wood Ridge between Stony Lane and Buck Road

-Continue meeting with residents to identify lateral location and depth

-Saw Cutting on Woodridge and Westaway will continue

-Drilling on Westaway will continue

-Soils sampling for the disposal site

January 31, 2020

252LF of pipe was installed on Woodridge and 180LF in the easement off Lower State Road.  We are still experiencing blue rock at 4 feet above invert as well as significant water in the trench on the easement off Lower State Road.  Test pits for rock depth in other areas will be completed in the next week.  Drilling on Westaway is continuing.  Erosion and sedimentation controls were checked to protect the creek from runoff and inlet covers were checked.  Meetings with residents in the construction area for lateral location stakes is continuing.

In the next week weather and conditions permitting we will expect to install:

-200 Lf of sewer main Woodridge and MH#32 near Buck Road

-MH PS-4 and sewer and force main to MH PS-5 in the easement between Lower State Road and Old New Road

-Lateral stubs for the properties on Wood Ridge where sewer main has been installed

-Continue meeting with residents to identify lateral location and depth

-Saw Cutting on Woodridge and Westaway will continue

-Drilling on Westaway will continue

January 28, 2020

192LF of pipe was installed on Woodridge and in the easement off Lower State Road.  We are still experiencing blue rock at 4 feet above invert as well as significant water in the trench on the easement off Lower State Road.  Test pits for rock depth in other areas will be completed in the next two weeks.  Drilling on Westaway is continuing.  Erosion and sedimentation controls were checked to protect the creek from runoff and inlet covers were checked.  Meetings with residents in the construction area for lateral location stakes is continuing.

In the next week weather and conditions permitting we will expect to install:

-100 Lf of sewer main Woodridge and MH#31

-100 LF of force main and MH PS-4 and sewer and force main to MH PS-5 in the easement between Lower State Road and Old New Road

-Test pits for soil samples in areas yet excavated will be performed

-Continue meeting with residents to identify lateral location and depth

-Saw Cutting on Woodridge and Westaway will continue

-Drilling on Westaway will continue

January 17, 2020

146LF of pipe was installed on Woodridge and in the easement off Lower State Road.  We are still experiencing blue rock at 4 feet above invert as well as significant water in the trench on the easement off Lower State Road.  Lateral stubs for all remaining Stony Lane residences has been completed.  Test pits for rock depth in other areas will be completed in the next two weeks.  Drilling on Westaway is continuing. Erosion and sedimentation controls were checked to protect the creek from runoff and inlet covers were checked.  Meetings with residents in the construction area for lateral location stakes is continuing.

In the next week weather and conditions permitting we will expect to install:

-200 Lf of sewer main Woodridge and MH#31

-150 LF of sewer main and force main and MH PS-4 in the easement between Lower State rd. and Old New Road

-(2) creek crossings in the easement off Lower State Road

-Continue meeting with residents to identify lateral location and depth

Saw Cutting on Woodridge and Westaway will continue

January 10, 2020

134LF of pipe was installed on Stony Lane and in the easement off Lower State Road.  Manhole#30 was installed at Stony Lane and Woodridge.  Lateral stub to 108 Pebble Ridge rd. was also completed.  Test pits for rock depth completed on Woodridge and Westaway show additional drilling is needed.  Erosion and sedimentation controls were checked to protect the creek from runoff and inlet covers were checked.  Meetings with residents in the construction area for lateral location stakes is continuing.  The drilling of Stony Lane is completed. Additional drilling on Westaway will begin soon.

In the next week weather and conditions permitting we will expect to install:

-3 Lateral stubs on Stony Lane

-300 Lf of sewer main Woodridge and MH#31

-200 LF of sewer main and force main and MH PS-4in the easement between Lower State rd. and Old New Road

-Continue meeting with residents to identify lateral location and depth

-Saw Cutting on Woodridge and Westaway will continue

January 3, 2020

140 LF of pipe was installed on Stony Lane and in the easement off Lower State Road. Test pits for rock depth completed on Woodridge and Westaway show additional drilling is needed. Significant rock at the bottom of the drilled area on Stony Lane and significant water in the trench off Lower State Road has slowed production. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Meetings with residents in the construction area for lateral location stakes is continuing.  The drilling of Stony Lane is completed.  Additional drilling on Westaway will begin soon.

In the next week weather and conditions permitting we will expect to install:

-Remaining pipe on Stony Lane Road

-Manhole #30 on Stony Lane Road at Woodridge

-Lateral stubs for residents on Stony Lane Road

-Continue meeting with residents to identify lateral location and depth

-Continue in the easement off Lower State Road installing manhole #3 and #4 with 300 LF of gravity main and force main

-Cutting on Woodridge and Westaway will continue

December 31, 2019

70 LF of pipe was installed on Stony Lane. Test pits for rock depth completed on Woodridge and Westaway show additional drilling is needed. Significant rock at the bottom of the drilled area on Stony Lane and significant water in the trench off Lower State Road has slowed production. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Meetings with residents in the construction area for lateral location stakes is continuing.  The drilling of Stony Lane is completed.

In the next week weather and conditions permitting we will expect to install:

-100 LF of pipe on Stony Lane Road

-Manhole #30 on Stony Lane Road

-Continue meeting with residents to identify lateral location and depth

-Due to the short holiday week we will only have one crew who will continue the installation of sewer on Stony Hill Road

December 23, 2019

28 LF of pipe was installed on Stony Lane. Test pits for rock depth were completed on Woodridge and Westaway. Significant rock at the bottom of the drilled area on Stony Lane and significant water in the trench off Lower State Road has slowed production. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Meetings with residents in the construction area for lateral location stakes is continuing.  The drilling of Stony Lane is completed.

In the next week weather and conditions permitting we will expect to install:

-170 LF of pipe on Stony Lane Road

-Manhole #30 on Stony Lane Road

-Continue meeting with residents to identify lateral location and depth

-Due to the holiday week we will only have one crew who will continue the installation of sewer on Stony Hill Road

-Test pits will be dug on Woodridge and Westaway to confirm rock depth as well as saw cutting of the roadway

December 12, 2019

Due to weather and cleanup work needed no additional pipe was installed. Test pits for rock depth we completed on Woodridge and Westaway. Significant rock at the bottom of the drilled area on Stony Lane and significant water in the trench off Lower State Road has slowed production. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Meetings with residents in the construction area for lateral location stakes is continuing. The drilling of Stony Lane is continuing. Paving has been completed on Pebble Ridge Road.

In the next week weather and conditions permitting we will expect to install:

-Sewer Main and Force Main installation will continue from Lower State Road in the easement area off of Old New Road

-200 LF of pipe on Stony Lane Road

-Manhole #30 on Stony Lane Road

-The driller to complete pre-drill of Stony Lane Road

-Continue meeting with residents to identify lateral location and depth

-Due to the holiday week we will only have one crew who will continue the installation of sewer on Stony Hill Road

-Test pits will be dug on Woodridge and Westaway to confirm rock depth as well as saw cutting of the roadway

December 06, 2019

In the past week construction installed 56 LF of pipe on Stony Lane and the easement off Lower State Road.  Manholes #PS3 and #29 are being installed today.  Significant rock at the bottom of the drilled area on Stony Lane and significant water in the trench off Lower State Road has slowed production.  Erosion and sedimentation controls were checked to protect the creek from runoff and inlet covers were checked.  Meetings with residents in the construction area for lateral location stakes is continuing.  The drilling of Stony Lane is continuing. Paving has begun on Pebble Ridge Road.

In the next week weather and conditions permitting we will expect to install:

-Sewer Main and Force Main installation will continue from Lower State road in the easement area off of Old New Road

-200 LF of pipe on Stony Lane

-Manhole #30 on Stony Lane

-The driller is continuing to pre-drill Stony Lane

-Continue meeting with residents to identify lateral location and depth

-One crew will continue the installation of gravity main and force main in Lower State Road and the 2nd crew will install sewer on Stony Hill Road

-Test pits will be dug on Woodridge and Westaway to confirm rock depth as well as saw cutting of the roadway

November 22, 2019

In the past week construction installed 300 LF of pipe on Stony Lane and the easement off Lower State Road.  Significant rock at the bottom of the drilled slowed production.  Erosion and sedimentation controls were checked to protect the creek from runoff and inlet covers were checked.  Meetings with residents in the construction area for lateral location stakes is continuing.  The drilling of Stony Lane is continuing. Paving is scheduled for Dec 3rd on Pebble Ridge Road.

In the next week weather and conditions permitting we will expect to install:

-Sewer main and force main installation will continue from Lower State road in the easement area off of Old New Road

-150 LF of pipe on Stony Lane

-Manhole #29 on Stony Lane

-The driller is continuing to pre-drill Stony Lane

-Continue meeting with residents to identify lateral location and depth

-Milling and Paving of Portions of Pebble Ridge Road are expected to begin weather permitting by 12-3-19 at the latest

-One crew will continue the installation of gravity main and force main in Lower State Road and the 2nd crew will install sewer on Stony Hill road

-Test pits will be dug on Woodridge and Westaway to confirm rock depth

November 15, 2019

In the past week construction installed 140 LF of pipe on Stony Lane.  Significant rock at the bottom of the drilled slowed production.  Erosion and sedimentation controls were checked to protect the creek from runoff and inlet covers were checked.  Meetings with residents in the construction area for lateral location stakes is continuing.  The drilling of Stony Lane is continuing.  Paving is scheduled for the 19th on Pebble Ridge Road.

In the next week weather and conditions permitting we will expect to install:

-Sewer Main and Force Main installation will continue from Lower State road in the easement area off of Old New Road

-150 LF of pipe on Stony Lane

-Manhole #29 on Stony Lane

-The driller is continuing to pre-drill Stony Lane

-Continue meeting with residents to identify lateral location and depth

-Milling and paving of portions of Pebble Ridge Road are expected to begin weather permitting by 11-19-19 at the latest

-One crew will continue the installation of gravity main and force main in Lower State Road and the 2nd crew will install sewer on Stony Hill road

November 08, 2019

In the past week construction installed the pipes for the trunk line and force main from the Pump Station across Lower State Road.  Manholes on Pebble Ridge Road were adjusted and purged ahead of the upcoming paving work.  Significant rock outcroppings and water were encountered during the excavation of Lower State Road.  Erosion and sedimentation controls were checked to protect the creek from runoff and inlet covers were checked.  Meetings with residents in the construction area for lateral location stakes is continuing.  The drilling of Stony Lane in advance of our excavating of the area is continuing.

In the next week weather and conditions permitting we will expect to install:

-Sewer Main and Force Main installation will continue from Lower State Road in the easement area off of Old New Road

-300 LF of pipe on Stony Lane

-Manhole #29 on Stony Lane

-The driller is continuing to pre-drill Stony Lane

-The paving contractor will pave the crossing of Lower State Road on Nov 11th

-Continue meeting with residents to identify lateral location and depth

-Milling and paving of portions of Pebble Ridge Road are expected to begin weather permitting by 11-18-19 at the latest

-One crew will begin the installation of gravity main and force main in Lower State Road and the 2nd crew will install sewer on Stony Hill Road

-Concrete restoration will also be conducted

November 01, 2019

In the past week construction installed the remaining lateral connections for the homes on Pebble Ridge Road.  Saw cutting of Lower State Road was completed.  Significant rock outcroppings have been encountered 1-2 feet above invert (bottom of trench).  Erosion and sedimentation controls were checked to protect the creek from runoff and inlet covers were checked.  Restoration crews completed work on the easement at Shady Brook Circle.  Meetings with residents in the construction area for lateral location stakes is continuing.  The drilling of Stony Lane in advance of our excavating of the area is continuing.

In the next week weather and conditions permitting we will expect to install:

-Sewer Main and Force Main installation (approx. 75 feet of each crossing Lower State Road) from the pump station

-300 LF of pipe on Stony Lane

-Manhole #29 on Stony Lane

-The driller is continuing to pre-drill Stony Lane

-Continue meeting with residents to identify lateral location and depth

-Milling and Paving of Portions of Pebble Ridge Road are expected to begin weather permitting by 11-18-19 at the latest

-One crew will begin the installation of gravity main and force main in Lower State Road and the 2nd crew will install sewer on Stony Hill road

-Concrete restoration will also be conducted

October 25, 2019

In the past week construction installed additional lateral connections for the homes on Pebble Ridge Road. Significant rock outcroppings have been encountered 1-2 feet above invert (bottom of trench).  Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked.  Restoration crews began work on the easement at Shady Brook Circle.  Meetings with residents in the construction area for lateral location stakes is continuing.  The drilling of the deepest parts of Stony Lane in advance of our excavating of the area is continuing.

In the next week weather and conditions permitting we will expect to install:

-300 LF of pipe if on Stony Lane

-Manholes #29 on Stony Lane

-Continue to install the last of the lateral connection stubs for residences on Pebble Ridge Road between Stony Lane and Turk Road

-The driller is continuing to pre-drill Stony Lane. They will be working on Saturday 10-26-19 as well

-Continue meeting with residents to identify lateral location and depth

-Milling and Paving of Portions of Pebble Ridge Road are expected to begin weather permitting

-Saw cutting and installation of main and force main in Lower State Road will begin. The 2nd crew is expected to start on Nov 6th

-Restoration of the easement areas will also be continuing in the area of Shady Brook Circle

-Concrete restoration will also be conducted

October 18, 2019

In the past week construction installed 55 feet of pipe and Manhole MH #28 which finishes the main installation on Pebble Ridge Road.  Significant rock outcroppings have been encountered 1-2 feet above invert (bottom of trench).  Erosion & sedimentation controls were checked to protect the creek from runoff and inlet covers were checked.  Crews continued to cleanup and remove material and equipment from Shady Brook Circle.  Meetings with residents in the construction area for lateral location stakes is continuing.  The drilling of the deepest parts of Stony Lane in advance of our excavating of the area is continuing.

In the next week weather and conditions permitting we will expect to install:

-300 LF of pipe if conditions permit

-Manholes #29 if conditions permit

-Continue to install the lateral connection stubs for residences on Pebble Ridge Road between Stony Lane and Turk Road (13)

-The driller is continuing to pre-drill Stony Lane

-The crew will move back to Stony Lane when the driller has performed his work and continue on to Woodridge as conditions allow

-Continue meeting with residents to identify lateral location and depth

-Restoration will begin on the easement from Shady Brook Circle down to the crossing location for Militia Hill Rd. expected to take at least a week weather permitting

-Concrete restoration on curbing on Shady Brook Cir will also be conducted around the same time as the easement restoration weather permitting

October 11, 2019

In the past week construction installed 500 feet of pipe and Manhole MH #27 as they continue down Pebble Ridge Road towards Turk Road.  Significant rock outcroppings have been encountered 1-2 feet above invert (bottom of trench).  Erosion & sedimentation controls were checked to protect the creek from runoff and inlet covers were checked.  Meetings with residents in the construction area for lateral location stakes is continuing.  The drilling of the deepest parts of Stony Lane in advance of our excavating of the area is continuing.

In the next week (short Week) weather and conditions permitting we will expect to install:

-30 linear feet of pipe and continue on Pebble Ridge Road towards Turk Road

-Manholes #28

-The lateral connection stubs for residences on Pebble Ridge Road between Stony Lane and Turk Road

-The driller is continuing to pre-drill Stony Lane

-The crew will move back to Stony Lane when the driller has performed his work and continue on to Woodridge as conditions allow

-We will also be moving stockpiles out of Shady Brook Cir to a new location

-Continue meeting with residents to identify lateral location and depth

October 4, 2019

In the past week construction installed 500 feet of pipe Manholes MH #25 and MH #26 as they continue down Pebble Ridge road towards Turks road.  Significant rock outcroppings have been encountered 1-2 feet above invert (bottom of trench).  Erosion & sedimentation controls were checked to protect the creek from runoff and inlet covers were checked.  Meetings with residents in the construction area for lateral location stakes is continuing.  Due to the encountering of the blue dense rock at Stony Lane the drilling company has been brought in and is drilling the deepest parts of Stony Lane in advance of our excavating of the area.

In the next week weather and conditions permitting we will expect to install:

-500 linear feet of pipe and continue on Pebble Ridge Road towards Turk Road

-Manholes #27 and possibly MH#28 if subsurface conditions improve (less rock)

-The lateral connection stubs for residences on the section of main (if any)

-The driller is continuing to pre-drill Stony Lane

-The crew will move back to Stony Lane when the driller has performed his work and continue on to Woodridge as conditions allow

-Continue meeting with residents to identify lateral location and depth

September 27, 2019

In the past week construction installed 2 laterals and casting for Manhole MH #24 as well as raised some castings on the other installed manholes on Pebble Ridge Road.  Significant rock outcroppings have been encountered 4-5 feet above invert (bottom of trench).  Erosion & sedimentation controls were checked to protect the creek from runoff and inlet covers were checked.  Meetings with residents in the construction area for lateral location stakes is continuing.  Due to the encountering of the blue dense rock at Stony Lane we will be continuing down Pebble Ridge Road while we schedule a driller to come in and drill the rock on Stony Lane and other suspected locations in the work area over the next 6-8 weeks.

In the next week weather and conditions permitting we will expect to install:

-Continue on Pebble Ridge Road from Shady Brook Circle to the end on Pebble Ridge Road just short of Turk Road

-Manholes #25, 26 and #27

-The lateral connection stubs for residences on the section of main (if any)

-The driller is expected to start at Stony Lane on Monday 9-30

-The crew will move back to Stony Lane when the driller has performed his work and continue on to Woodridge as conditions allow

-Continue meeting with residents to identify lateral location and depth

September 20, 2019

In the past week construction installed approx. 200 feet of pipe and set Manhole MH #24 on Pebble Ridge Road at Stony Lane.  Significant rock outcroppings have been encountered 4-5 feet above invert (bottom of trench).  Erosion & sedimentation controls were checked to protect the creek from runoff and inlet covers were checked.  Meetings with residents in the construction area for lateral location stakes is continuing.  Due to the encountering of the blue dense rock at Stony Lane we will be continuing down Pebble Ridge Road while we schedule a driller to come in and drill the rock on Stony Lane and other suspected locations in the work area over the next 6-8 weeks.

In the next 2 weeks weather and conditions permitting we will expect to install:

-Continue on Pebble Ridge Road from Shady Brook Circle to the end on Pebble Ridge Road just short of Turk Road

-Manholes #25, 26 and #27

-The lateral connection stubs for residences on the section of main (if any)

-The crew will move back to Stony Lane when the driller has performed his work and continue on to Woodridge as conditions allow

-The second crew who will begin at the Pump Station on Lower State Road is schedule to start at the end of October

-Continue meeting with residents to identify lateral location and depth

September 6, 2019

In the past week construction installed approximately 300 feet of pipe and set Manhole MH #21 on Pebble Ridge Road between Shady Brook Circle and Stony Lane.  Significant rock outcroppings have been encountered 2-4 feet above invert (bottom of trench).  Erosion and sedimentation controls were checked to protect the creek from runoff and inlet covers were checked.  Meetings with residents in the construction area for lateral location stakes is continuing.  BCWSA and Doylestown Township representatives met to coordinate trench paving and roadway restoration as the Township replaces stormwater pipes in the areas BCWSA has installed sanitary sewer mains.

In the next 2 weeks weather permitting we will expect to install:

-Continue on Pebble Ridge Road from Shady Brook Circle onto Stony Lane and continuing on the north side of Woodridge.  Approximately 1000 LF of sewer main

-Manholes #22 and #23

-The lateral connection stubs for residences on the section of main (if any)

-The crew will continue to Woodridge as conditions allow

-Continue meeting with residents to identify lateral location and depth

August 30, 2019

In the past week construction installed approximately 300 feet of pipe up to and set Manhole MH #20.  They installed the remaining lateral tees for the residences on Pebble Ridge Road.  Rock was encountered about 1-2 feet above invert (bottom of trench).  Erosion & sedimentation controls were checked to protect the creek from runoff and inlet covers were checked.  Letters to the residents who will have lateral tees set in the next 2-4 weeks were sent out on 8-9-19.  Additional letters will be sent out next week for the sections we will be installing main for over the next six weeks.

In the next 2 weeks weather permitting we will expect to install:

-Continue the next leg of Pebble Ridge Road from Shady Brook Circle up to and onto Stony Lane. Approximately 200 LF of sewer main

-Manholes #21 and #22

-The lateral connection stubs for residences on the section of main (if any)

-The crew will continue to Woodridge as conditions allow

-Continue meeting with residents to identify lateral location and depth

August 23, 2019

In the past week construction installed approximately 600 feet of pipe up to and set Manhole MH #18 then continued to install main and set Manhole #19 on Pebble Ridge Road.  They installed lateral tees for 3 additional residences on Pebble Ridge Road.  Rock was encountered about 1-2 feet above invert (bottom of trench).  Erosion & Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked.  Letters to the residents who will have lateral tees set in the next 2-4 weeks were sent out on 8-9-19.

In the next 2 weeks weather permitting we will expect to install:

-Continue the approximately 300 linear feet of sewer main up to manhole (#20) on Pebble Ridge Road to complete that leg of the sewer

-Manhole #20

-The lateral connection stubs for the remaining residents on this leg of Pebble Ridge road

-The next leg of the trunk line will be started on Pebble Ridge road going up Stony lane to Woodridge

-Continue meeting with residents to identify lateral location and depth

August 09, 2019

In the past week construction installed approximately 100 feet of pipe from Manhole MH #17 on Pebble Ridge Road. They installed lateral tees for 487 Pebble Crest, 203, 206, and 215 Pebble Ridge Road.  Rock was encountered about 1-2 feet above invert (bottom of trench). Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked. Letters to the residents who will have lateral tees set in the next 2-4 weeks were sent out on August 9, 2019.

In the next 2 weeks weather permitting we will expect to install:

-Continue the approximately 900 linear feet of sewer main up to manhole (#20) on Pebble Ridge Road to complete that leg of the sewer

-Manholes #18, #19,#20

-The lateral connection stubs for residents at 218, 227, 230 Pebble Ridge Road, if rock is mild, additional lateral tees as we progress up Pebble Ridge road

-Continue meeting with residents to identify lateral location and depth

August 02, 2019

In the past week construction installed approximately 430 feet of pipe from Manhole #15 to just short of MH #17 and they are digging to install another 70 feet of pipe and set Manhole #17 today. They installed lateral tee for 191 Pebble Ridge Road.  Rock was encountered about 1-2 feet above invert (bottom of trench).  Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked.

In the next 2 weeks weather permitting we will expect to install:

-Continue the approximately 1000 linear feet of sewer main up to manhole (#20) on Pebble Ridge Road to complete that leg of the sewer

-Manholes #18, #19,#20

-The lateral connection stubs for residents at 203, 206 Pebble Ridge Road, 487 Pebble Crest and, if rock is mild, additional lateral tees as we progress up Pebble Ridge Road

-Continue meeting with residents to identify lateral location and depth

July 27, 2019

In the past week construction installed 120 feet of pipe from Manhole #14 to #15 and they are digging to install another 150 feet of pipe and set Manhole #16 today. They installed lateral tees for the reaming Shady Brook Circle homes and installed lateral tees for 165 & 184 Pebble Ridge Road. Minor rock was encountered about 1-2 feet above invert (bottom of trench). This was a short week due to delivery and First Aid / CPR Training. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked.

In the next  week weather permitting we will expect to Install:

– Continue the approx. 1000 linear feet of sewer main up to manhole (#17) on Pebble Ridge Road

– Manhole #17

– The lateral connection stubs for residents at 191, 203, 206 Pebble Ridge Road

– Continue meeting with residents to identify lateral location and depth

July 27, 2019

In the past week construction installed 120 feet of pipe from Manhole #14 to #15 and they are digging to install another 150 feet of pipe and set Manhole #16 today. They installed lateral tees for the reaming Shady Brook Circle homes and installed lateral tees for 165 & 184 Pebble Ridge Road. Minor rock was encountered about 1-2 feet above invert (bottom of trench). This was a short week due to delivery and First Aid / CPR Training. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked.

In the next  week weather permitting we will expect to Install:

– Continue the approx. 1000 linear feet of sewer main up to manhole (#17) on Pebble Ridge Road

– Manhole #17

– The lateral connection stubs for residents at 191, 203, 206 Pebble Ridge Road

– Continue meeting with residents to identify lateral location and depth

July 19, 2019

In the past 2 weeks BCWSA has been continuing work from the end of the easement area just outside of the Shady Brook Circle. We continued to encounter significant rock outcroppings causing some minor field adjustments. Severe weather hampered progress on 3 occasions. We installed 2 manholes, 300 linear feet of sewer main out and onto Pebble Ridge road. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked.

In the next  2 weeks weather permitting we will expect to Install:

– Approx. 1000 linear feet of sewer main up to manhole (#17) on Pebble Ridge Road

– Manholes #15, #16 & #17

– The lateral connection stubs for residents at 165, 184, 191, 203, 206 Pebble Ridge Road

– Continue meeting with residents to identify lateral location and depth

June 28, 2019

In the past week BCWSA has been continuing work in the easement area between Almshouse Rd. and Shady Brook Circle. We continue to encounter significant rock outcroppings causing some minor field adjustments. We installed 1 manhole, 150 linear feet of sewer main. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were checked on Shady Brook Circle.

In the next 2 weeks we will expect to Install:

-Approx. 200 linear feet of sewer main up to manhole (#14) on Shady Brook Circle.
– The lateral connection stubs for remaining residences on Shady Brook Circle.
– Drop back and do the final creek crossing for Militia Hill connection.
– Continue laying sewer main out of Shady Brook onto Pebble Ridge road placing lateral stubs for residences as we pass them.
– Continue meeting with residents to identify lateral location and depth.

June 21, 2019

In the past week BCWSA has been continuing work in the easement area between Almshouse Rd. and Shady Brook Circle. We continue to encounter minor rock outcroppings. We installed 1 manhole, 50 linear feet of sewer main. Due to weather conditions we were only able to work for 3 days this week. Erosion and Sedimentation controls were checked to protect the creek from runoff and inlet covers were set on Shady Brook Circle.

In the next 2 weeks we will expect to Install:

-Approx. 100 linear feet of sewer main up to manhole (#13)
-Last manhole (#13) that resides in the cul-de-sac of Shady Brook Circle
– The lateral connection stub for Residence #164 Shady Brook Circle
– Drop back and do the final creek crossing for Militia Hill connection
– Continue laying sewer main out of Shady Brook onto Pebble Ridge road placing lateral stubs for residences as we pass them

June 14, 2019

In the past week BCWSA has been continuing work in the easement area between Almshouse Rd. and Shady Brook Circle. We continue to encounter minor rock outcroppings. We have installed 1 manhole, 165 linear feet of sewer main and the creek crossing connection for the Militia Hill Rd area customers. Additional Erosion and Sedimentation controls were installed to protect the creek from runoff.

In the next week we will expect to install:

– Last 2 manholes to the roadway of Shady Brook Circle
– Approx. 150 linear feet of sewer main
– The lateral connection stub for Residence #164 Shady Brook Circle

June 7, 2019

In the past week BCWSA has working in the easement area between Almshouse Rd. and Shady Brook Circle. We encountered minor rock outcroppings. We have installed 2 manholes and  322 linear feet of sewer main. Connection stubs for lateral tie ins at 965 and 970 are also complete.

In the next two weeks we will expect to Install:

– 3 manholes up to the roadway of Shady Brook Circle

– 525 linear feet of sewer main

– Bypass equipment to allow us to complete the creek crossing from the easement to Militia Hill Rd.
– The lateral connection stub for Residence #164 Shady Brook Circle

June 4, 2019 

John Butler, Bucks County Water & Sewer Authority COO, presented at the June 4 Board of Supervisors meeting. He spoke about the project timeline and addressed questions and concerns from the public. View the video here!

May 28, 2019

The sewer line installation is continuing. We have crossed over Almshouse Road near Militia Hill Road. We will be working in the easement up to Shady Brook Circle over the next two (2) weeks. Weather permitting.

May 6, 2019 

The drilling of the rock (at the Both property) ended on 4/25 , Construction picked up with the sewer main installation again on Monday 4/29. The rock was able to come out with some hammering involved. By the end of 5/3 construction installed 168 LF. down the driveway. We plan on being at the end of the Both property and moving across Almshouse road in 2 weeks (weather permitting).  We expect the installation rate to increase significantly.

April 12, 2019 

We are working on the driveway portion of the Both property at Almshouse and Militia Hill roads. We are also continuing to raise the grade along the easement off Militia hill road to aide in expediting the pipe installation. We have hit significantly dense rock on the Both property and have to start drilling every one foot on center of the trench so we can break the rock. Currently the rock is destroying the bits we use to break it apart. We expect the drilling to take one to two weeks. We are currently only about 2 weeks off our schedule. Once the drilling is completed we will update the projections of the timing of the work. Some minor design changes are being made to reduce the rock being encountered (based on boring results) and to streamline the pipe work.

April 1, 2019 Last week the Construction crew hammered and grinded the 14 LF x 3’D to get to the location of Manhole #4 . Construction hammered and grinded a 4.5’d x8’ x8’w to get the area where manhole #4 was to be set. Construction set Manhole #4 on 3/28/2019 and installed  18’ to make the connection from Manhole # 3a to Manhole # 4, Crew also back-filled around Manhole #4 and back-filled the open trench between Manhole #3a and Manhole #4. 3/29/2019 crew clean-up remaining material and Haul in 300+ Tons of stone from manhole #4 to Manhole #5.

This Week we anticipate to be in the blue rock for another 30 to 60 ft. we are coming out of it with the test holes that we excavated to see if there was rock in various locations. In the beginning we will be grinding about 2-3’of rock in the trench, but hopefully it will be dropping off as we are coming up with the slope of the pipe. As long as the weather holds out we anticipate crossing Almshouse Rd. in 2 weeks.

February 26, 2019 Rutledge Excavating will be start clearing in the right of way on Thursday, February 28. The clearing will start on Old New Road and work its up to Willow.

February 22, 2019 Due to weather and sewer alignment adjustment approvals from DEP the project has been on hold and the crew sent to do other work. We expect to restart the Pebble Ridge work mid next week (2-27-19). We will update the schedule of milestones once we are underway again. All work is weather permitting.

December 28, 2018 “We have been hitting significant rock in the driveway of the Both Property. We have begun discussing some alternative ways to avoid the rock as it has slowed down the production rate. Coupled with weather we are progressing slowly. We hoped to be across Militia Hill next week but we anticipate the rock issue will push us back 3-4 weeks”

November 2, 2018 “Excavation has begun and we have installed 300 lf of 8” SDR-26 (pipe thickness) and Manholes CV#1 and CV#2.  We have begun to encounter rock which were are ripping out with our machine.

The week of the 5 of November we expect to continue installing pipe as well as manholes CV#3 and CV#4. This run will be a slow moving one as the cut in depth of this line will be approximately 22 feet below street level.  As always the schedule is  weather dependent.”

October 12, 2018 “BCWSA will continue saw cutting on Militia hill rd. the week of 10-15. Due to weather we have not been able to excavate at the interceptor, therefore we will be starting excavation at the easement next to Militia Hill rd. by the week of 10-22 possible sooner if weather permits.”

September 14, 2018 “ Material delivery for the first section (Almshouse and Militia hill roads) has been completed. Pipe installation has been delayed due to creek levels and rain expected next week. We expect to begin installation the week of 9-24-18”


August 24, 2018  Click Here to view the newest press release from BCWSA.


July 27, 2018 Letter from BCWSA.  Click Here to view the letter


*Beginning the week of July 23rd Gilmore and Associates will begin the stake out for the sewer project on those properties that provided easements.

*BCWSA are still on schedule to begin work on the sewer project the beginning of August. They will be starting with clearing along the creek side of the project before moving into the neighborhood.


Pebble Ridge/Woodridge & Vicinity Approved Agreement with BCWSA

October 30, 2017 Click Here to view Resolution No. 1980

Pebble Ridge/Woodridge & Vicinity Final Draft Agreement with BCWSA

Click Here to view the Pebble Ridge/Woodridge Area Sanitary Sewer Construction Agreement

Road Program Curbing and Paving Projects
Weekly Updates

Week of 9/14

SAS Geospatial, LLC (surveyor) will start survey stake-out for the curbing project on the following roads.  The surveyor will be in a vehicle identified with their company logo, they will also be wearing florescent survey attire, and they will be following Covid 19 protocols (wearing of masks and staying socially distant from residents).

  • Pebble Crest Road
  • Pebble Ridge Road
  • Shady Brook Circle

Survey stake-out will include the placement of wood survey stakes approximately every 50’ or less, 5’ behind the exiting edge of the combination curb and gutter within the existing roadway right-of-way. Residents are requested not to remove or disturb the survey stakes, as replacing them will add delay and cost to the project.

Week of 9/21

Reasmstown Excavating will mobilize on site to start the removal of the existing combination curb and gutter, prepare the new curb sub-base for Prieto Corporation to bring in a curb machine to install the new curbing.

Residents should be advised of the following:

  • The exiting combination curb and gutter will be removed in front of their property and there will be open trenches at times.  The curb and gutter in front of their driveway will be removed and temporarily replaced with stone.
  • Access to residential driveways will be restricted temporarily during the day (when work is in being done in front of their property), however access will be restored as soon as the demolition/removal is complete.
  • When the new curbing is installed, access will be restricted to residential driveways for a day or two while the concrete sets.
  • Driveway grades will be adjusted as needed to meet the new curb elevation.  Maximum length of driveway adjustment is anticipated not to exceed 20 feet from the curbline into the properties, and may be less in most cases.
  • Contractors will be allowed to store equipment and material within the existing road right-of-way, which includes in the roadway and/or the grass area immediately behind the exiting curb and within public right-of-way.
PENNVEST Loan Information

6/6/2018 Township Completes Closing on the PENNVEST Loan.

Click Here to view the attached letter with a tentative schedule and timeline for construction.

Public Water Survey in Pebble Ridge/Woodridge

Click Here to view the Municipal Authority’s letter to residents whose purpose is to gauge the interest in having public water in the surrounding vicinity of the Pebble Ridge/Woodridge neighborhood.

Township Awards Bids and Approves Paperwork for PENNVEST Loan

On April 17, 2018 the Doylestown Township Board of Supervisors approved the bids for the pump station and the clearing and grubbing for the project. Click here for the article. Be advised that BCWSA still has to approve the bids.

Also, the Board approved the required paperwork associated with the PENNVEST loan. We anticipate closing on the loan in late May. We’ll post additional updates as information becomes available.

Low Interest Loan Application Approved

At their meeting on January 31, 2018 the PennVest Board approved the Township’s application for the low interest loan to pay for the costs associated with the construction and installation of the Pebble Ridge/Woodridge Sewer Project. The receipt of funds from PennVest is subject to a formal settlement, which the Township anticipates will occur within the next four to six months.  As indicated during meetings this past summer, the low interest loan interest rates and loan term offered to us by PennVest will be passed along and will be available to residents as part of a loan program offered through BCWSA to pay for each resident’s costs of the public portion of the Project.

In addition, BCWSA’s engineer Gilmore & Associates will be putting out bids for construction of the pump station, as well as clearing for the project. Permits for the project from PennDot, PA DEP and the Bucks County Conservation District are being finalized.

We still anticipate this project getting underway during the summer of 2018.

Ordinances

Click Here to view Ordinance No. 384

Below is the proposed and revised ordinance for consideration on 8/15/17. The Board of Supervisors adopted this ordinance at their meeting on 8/15/17.

Proposed Revised Sewer Ordinance

Related Past Documents and Materials:

Proposed Ordinance

Easements: On March 3rd, 2015 the Doylestown Township Board of Supervisors authorized the acquisition of the necessary easements for this project.  Once the easements are received, Bucks County Water and Sewer Authority will move forward with the bidding process.